Phase 3 of the school's "Building for the Future Project" – the infill between the Cottesloe Centre and the Founders Wing - began over the summer.
The new building brings together all the teaching facilities for Art, Ceramics, Textiles, Design Technology, Food Technology and ICT. It was completed in time for the start of the new academic year in September 2009.
|
|
Below are a selection of images charting the progress of the build:
Tuesday 23 June: The day of the Topping out Ceremony - Placing the final finial on the roof
|
|
|
|
Friday 19 June: The scaffolding is finally being taken down
|
Friday 20 March: The tiling is almost complete and the external brick work has begun.
|
Monday 23 February: The roof frame is now complete and tiling has begun.
|
Wednesday 4 February: Most of the roof framework is now complete and the walls have now reached the upper floors
|
|
Tuesday 20 January: The roof is now starting to go on and walls are being built.
|
|
|
Wednesday 17 December: The roof trusses are now in place and preparation has started so that the floors can be finished and the blockwork can begin
|
Tuesday 9 December: Putting in the floors
|
Wednesday 3 December: Working on the frame
|
Monday 1 December: More of the steel frame going up
|
Friday 28 November: The steel frame going up
|
Tuesday 25 November: The completed slab
Tuesday 11 November: Setting out the steel for the reinforced slab
Tuesday 14 October: Digging the foundations